How Much Concrete for a 30-Inch Round Footing 48 Inches Deep?
30″ diameter × 48″ deep round footing: 19.635 ft³ (0.7272 yd³), exact bag estimates and a 10% planning example.
A 30″ diameter × 48″ deep round footing holds 19.635 ft³ (0.7272 yd³) of concrete before a placement allowance. Its circular plan area is 4.9088 ft². The quantity is calculated as a straight cylinder, not as a square excavation or a bell-shaped footing.
The 30″ circular section is a relatively wide excavation and a substantial placement; verify the construction sequence and equipment before planning a bag-only pour. At 48 inches, utility locating, excavation safety, access, and the approved bearing elevation are especially important; a deeper hole is not automatically a better footing. The page estimates material for the dimensions shown; soil bearing, supported loads, reinforcement, frost exposure, and post anchorage are separate design checks. If the actual pier has a widened base or concrete above the stated depth, calculate that additional geometry separately.
Quick Answer
One 30″ diameter × 48″ deep round footing: 19.635 ft³ (0.7272 yd³) before waste. With a 10% example allowance, the planned volume is 21.5985 ft³ (0.7999 yd³). The appropriate allowance depends on the actual form, excavation and placement conditions.
Base quantities: 66 × 40 lb, 44 × 60 lb, or 33 × 80 lb bags. With 10% extra volume: 72 × 40 lb, 48 × 60 lb, or 36 × 80 lb bags. The calculation assumes mixed yields of 0.30/0.45/0.60 ft³ for 40/60/80 lb bags; check your exact product label.
Need a custom estimate? Use the Footing Calculator, try the concrete estimator for any pour, or browse footing size pages. All project pages.
How to Use This Footing Estimate
Use this sequence to estimate material for the 30″ diameter × 48″ deep geometry. It is not a structural design or a permit guide.
- Check the specified footing: verify that a 30″-diameter, 48″-deep cylinder is shown on the approved plan. Confirm design load, soil bearing, frost exposure, utilities, and the required base elevation. Plan safe excavation and access procedures appropriate to the soil and hole depth.
- Measure the form and cavity: measure the clear inside diameter and actual concrete-filled height. A flared base, irregular excavation, or raised pier extension adds volume beyond the simple cylinder.
- Calculate the concrete volume: use π × radius² × depth, with units converted consistently. This footing needs 19.635 ft³ before waste; a 10% example makes 21.5985 ft³.
- Combine multiple locations: for 4 identical cylinders, sum the concrete volumes first. The combined amount with 10% extra is 86.394 ft³, equivalent to 288 × 40 lb, 192 × 60 lb, or 144 × 80 lb bags.
- Plan material handling: one footing with 10% extra needs 36 80 lb bags (approximately 2,880 lb dry). Check access, form bracing, water, mixing rate, and ready-mix availability.
- Place and cure per the design: follow the engineer or local building requirements for preparation, reinforcement, embeds, placement, and consolidation, and the manufacturer’s instructions for mixing and curing.
Formula
Cylindrical footing formula: V = π × radius² × depth. Using inches directly, V (ft³) = 3.1416 × (diameter in inches ÷ 2)² × depth in inches ÷ 1,728.
For this 30″ × 48″ footing: 3.1416 × (30 ÷ 2)² × 48 ÷ 1,728 = 19.635 ft³. Divide the unrounded result by 27 to obtain 0.7272 yd³. The radius is half the diameter; no radius value is rounded before squaring.
10% example: original volume × 1.10 = 21.5985 ft³ (0.7999 yd³). Apply the extra percentage to cubic feet before converting to whole bags—do not multiply an already-rounded bag count by 1.10.
Worked Example
One 30″ diameter × 48″ deep footing: base volume 19.635 ft³ (0.7272 yd³). A 10% allowance gives 21.5985 ft³ (0.7999 yd³), requiring 72 × 40 lb, 48 × 60 lb, or 36 × 80 lb bags on the assumed yields.
4 identical round footings: 4 × the unrounded single-pier volume = 78.54 ft³ (2.9089 yd³). Allow 10% on the combined volume to reach 86.394 ft³ (3.1998 yd³), then round up once: 288 × 40 lb, 192 × 60 lb, or 144 × 80 lb bags. These totals can differ from multiplying individually rounded bag counts by 4.
Bag Count Estimate
- 36 bags of 80 lb concrete mix
- 48 bags of 60 lb concrete mix
- 72 bags of 40 lb concrete mix
Always verify the actual yield on the product label before buying materials.
Bag Counts by Waste Buffer for 30" diameter × 48" deep
These buffers are examples, not a universal recommendation. The right percentage depends on excavation accuracy, how precisely you measured, soil and ground conditions, and placement losses such as spillage or over-dig. This page uses 10% as its own planning figure.
| Buffer | Volume (ft³) | 80 lb bags | 60 lb bags | 40 lb bags |
|---|---|---|---|---|
| No buffer | 19.64 | 33 | 44 | 66 |
| +5% example | 20.62 | 35 | 46 | 69 |
| +10% example | 21.6 | 36 | 48 | 72 |
| +15% example | 22.58 | 38 | 51 | 76 |
When Bagged Concrete vs Ready-Mix Makes Sense
One footing at this size takes 36 × 80 lb bags under the 10% example, or roughly 2,880 lb of dry mix before water. This is a substantial bag-handling and mixing job; price ready-mix and verify access, placement duration, and the available crew before choosing bags.
For 4 identical footings, the combined 10%-adjusted volume is 3.1998 yd³ and the one-time rounded bag requirement is 144 bags of 80 lb mix. Ask suppliers about minimum loads, short-load charges, delivery scheduling, form access, and any need for pumping. Concrete volume and bag weight do not establish the bearing capacity of the foundation.
Common Uses for This Footing Size
A 30″-diameter cylinder has a noticeably larger concrete footprint than a narrow sonotube. It may be relevant when estimating a designed pier or column footing, but the larger diameter must not be mistaken for an engineering recommendation.
This 30″ diameter × 48″ deep cylinder has 4.9088 ft² of circular area and requires 19.635 ft³ of concrete before waste. At an unchanged diameter, 48 inches of concrete height doubles the volume of a 24-inch cylinder. Verify the intended filled height, excavation stability, and bearing elevation. If the design includes a flared base, bell, enlargement, or above-grade extension, include those separately. Soil conditions, frost requirements, structural loads, reinforcement and anchors require project-specific verification.
Common Mistakes to Avoid
Avoid these calculation and site-planning errors for the 30″ diameter × 48″ deep circular footing:
- Using 30″ as the radius rather than the diameter; the actual radius is 30/2 = 15″.
- Treating a 30″-diameter round hole like a 30″ × 30″ square excavation, which produces a different volume.
- Calculating bags from a rounded 0.73 yd³ display rather than from the full-precision cylinder volume.
- Adding a waste percentage to already-rounded whole bags rather than to concrete volume before bag rounding.
- Assuming a tube form or a straight hole includes the volume of a bell-shaped base or above-grade extension.
- Overlooking buried services and excavation stability when working with a 48-inch-deep footing cavity.
- Underestimating the handling, mixing continuity, and delivery logistics for a substantial number of bags.
Frequently Asked Questions
How much concrete does a 30-inch round footing 48 inches deep need?
A straight cylinder 30 inches in diameter and 48 inches deep contains 19.635 ft³ (0.7272 yd³) before waste. A 10% planning example is 21.5985 ft³ (0.7999 yd³). Add any bell, flared base or extension separately.
How many 40, 60 or 80 lb bags are needed for a 30″ × 48″ round footing?
Before waste, allow 66 of the 40 lb bags, 44 of the 60 lb bags, or 33 of the 80 lb bags. With 10% extra concrete volume, those totals are 72, 48, and 36 respectively. Assumed bag yields are 0.30, 0.45 and 0.60 ft³; use the yield stated on the actual bag.
Does a 48-inch-deep 30-inch round footing use twice as much concrete as one 24 inches deep?
Yes. With diameter held at 30 inches, a 24-inch-deep cylinder contains 9.8175 ft³, while the 48-inch version contains 19.635 ft³. This describes concrete quantity only, not which depth is appropriate for frost, soil or structural loads.
Is ready-mix worth comparing for this 30″ × 48″ round footing?
The 10% example for one cylinder is 36 80 lb bags, about 2,880 lb of dry mix. For four cylinders together, the volume totals 86.394 ft³ and 144 bags of 80 lb mix when rounded once. Compare the supplier’s minimum loads, delivery access, mixing capacity and scheduling; no fixed bag-count threshold makes ready-mix mandatory.
Keep Planning Your Concrete Project
Use the calculator, compare more footing pages, and review your estimate before buying materials.
Disclaimer: This page provides planning estimates only. Actual concrete needs vary with excavation accuracy, site conditions, local code requirements, bag yield, and supplier guidance. Always verify measurements before buying materials, and consult a qualified professional for structural or code-sensitive work.