How Much Concrete for an 18x18x36 Footing?

How Much Concrete for an 18x18x36 Footing?

18" × 18" × 36" square footing: 6.75 ft³ (0.25 yd³), with exact bag counts and a 10% planning example.

A 18" × 18" × 36" square footing contains 6.75 ft³ (0.25 yd³) of concrete before an allowance for excavation variation or spillage. Its 18" × 18" square base has a 2.25 ft² footprint; increasing depth changes the quantity without changing that base area.

For one footing, the bag count is significant enough to plan mixing cycles and handling before digging; repeat footings increase the batch total quickly. At 36 inches deep, confirm the specified bearing level, frost exposure, and excavation stability rather than assuming a deeper hole automatically meets code. Footing thickness, soil bearing, supported loads and reinforcement must come from the project design or local authority—not from the bag count.

Quick Answer

One 18" × 18" × 36" footing: 6.75 ft³ / 0.25 yd³ before waste. With a 10% example allowance, plan for 7.425 ft³ / 0.275 yd³. This allowance is a planning scenario, not a universal requirement.

Without waste: 23 × 40 lb, 15 × 60 lb, or 12 × 80 lb bags. With 10%: 25 × 40 lb, 17 × 60 lb, or 13 × 80 lb bags. Assumed mixed yields: 0.30/0.45/0.60 ft³ per 40/60/80 lb bag; always check the chosen product label.

How to Use This Footing Estimate

Use these steps to plan quantities for the 18" × 18" × 36" footing; they do not replace an approved structural design.

  1. Verify the design: confirm that a 18" × 18" × 36" footing is specified for the supported loads, soil bearing and local frost/depth rules. Locate underground utilities before excavation.
  2. Measure the concrete cavity: check clear internal dimensions of 18" long × 18" wide × 36" deep; account for any bell, extra base or irregular excavation separately.
  3. Estimate the concrete: one footing needs 6.75 ft³ before waste; a 10% example gives 7.425 ft³. Multiply by the actual number of identical footings.
  4. Choose delivery: for one footing with 10% extra, compare 25 40 lb, 17 60 lb, or 13 80 lb bags with ready-mix. Check the published yield of the exact bagged product.
  5. Plan the placement: follow the approved excavation, bearing preparation, formwork, reinforcement and anchorage details. Organize access, equipment and enough help for continuous placement.
  6. Mix, place and cure: follow the concrete product instructions for water, mixing, placement, consolidation and curing; do not treat a nominal curing age as automatic structural approval.

Formula

Rectangular or square footing volume: length × width × depth, with all three measurements in the same units. To calculate directly from inches, divide cubic inches by 1,728.

In cubic feet: (18 × 18 × 36) ÷ 1,728 = 6.75 ft³. In cubic yards: the unrounded ft³ result ÷ 27 = 0.25 yd³. Values shown here are rounded for display; bag counts use full precision.

10% planning example: base volume × 1.10 = 7.425 ft³, or 0.275 yd³. Because the allowance is applied to volume before dividing by bag yield, it is not the same as multiplying a previously rounded whole-bag count.

Worked Example

One 18" × 18" × 36" footing: 6.75 ft³ (0.25 yd³). With a 10% example allowance, 7.425 ft³ (0.275 yd³), equivalent to 25 × 40 lb, 17 × 60 lb, or 13 × 80 lb bags based on standard yields.

Three identical footings: 3 × 6.75 = 20.25 ft³ (0.75 yd³) before waste. Add 10% to the combined volume: 22.275 ft³ (0.825 yd³), then round up once to 75 40 lb, 50 60 lb, or 38 80 lb bags. This can differ from rounding each footing separately.

Bag Count Estimate

  • 13 bags of 80 lb concrete mix
  • 17 bags of 60 lb concrete mix
  • 25 bags of 40 lb concrete mix

Always verify the actual yield on the product label before buying materials.

Bag Counts by Waste Buffer for 18" x 18" x 36"

These buffers are examples, not a universal recommendation. The right percentage depends on excavation accuracy, how precisely you measured, soil and ground conditions, and placement losses such as spillage or over-dig. This page uses 10% as its own planning figure.

Buffer Volume (ft³) 80 lb bags 60 lb bags 40 lb bags
No buffer6.75121523
+5% example7.09121624
+10% example7.43131725
+15% example7.76131826

When Bagged Concrete vs Ready-Mix Makes Sense

For one footing, the 10% example needs 13 × 80 lb bags, approximately 1,040 lb of dry mix. Compare bag availability, mixer capacity and hauling time with a supplier quote rather than assuming bagged concrete is cheaper.

If there are three identical 18" × 18" × 36" footings, the combined volume with the same 10% example is 0.825 yd³. Order based on the combined measured cavities, not just the single-footing result; confirm truck access and what the supplier charges for short loads. Neither bag count nor material weight establishes the footing’s load-bearing capacity.

Common Uses for This Footing Size

This is a 18" square concrete footprint, so the material calculation applies to a symmetric footing below a post or pier if that geometry is specified on the plans. A square layout is simpler to measure than a non-square pad, but the area is not evidence of structural capacity.

The base area is 2.25 ft² and the concrete volume is 6.75 ft³. This page is useful for estimating a single cavity, comparing alternate depths, or calculating several identical footings. A 36" depth adds half again as much concrete as the same footprint at 24". That comparison is only about quantity, not a recommendation to make the footing deeper. Soil bearing, reinforcement, supported loads and local construction rules remain separate design checks.

Common Mistakes to Avoid

For this square footing, avoid these estimating and site-planning errors:

  • Confusing a 18" square base with a 18"-diameter round hole; square and circular volumes are different.
  • Ordering bags from a rounded 0.25 yd³ display instead of the precise 18" × 18" × 36" calculation.
  • Adding 10% to the already-rounded bag count instead of applying the example allowance to the concrete volume before rounding up.
  • Assuming that 36 inches of depth automatically satisfies a frost or structural requirement without checking the site and approved plans.
  • Using a generic bag yield without checking the specific manufacturer and mix type.
  • Overlooking bag transport, consistent mixing, consolidation and curing when placing multiple batches.

Frequently Asked Questions

How much concrete is in a 18" × 18" × 36" footing?

A single 18" × 18" × 36" square footing contains 6.75 ft³ (0.25 yd³) before waste. With a 10% example allowance, the planning quantity becomes 7.425 ft³ (0.275 yd³).

How many bags of concrete are needed for a 18" × 18" × 36" footing?

Without waste: 23 bags of 40 lb, 15 of 60 lb, or 12 of 80 lb. At a 10% example allowance: 25 of 40 lb, 17 of 60 lb, or 13 of 80 lb. These estimates assume 0.30, 0.45 and 0.60 ft³ of yield per respective bag; check the product label.

How much more concrete does a 36-inch depth use than 24 inches?

At the same 18" × 18" footprint, 24" depth uses 4.5 ft³ and 36" depth uses 6.75 ft³: 50% more concrete. The required depth is governed by design and site conditions, not material savings.

Is a 18" × 18" × 36" footing deep enough for a deck post?

Not necessarily. A 36" depth does not establish adequacy without the local frost depth, soil bearing, load and applicable footing rules. Follow the engineered or approved plan; the figures on this page are volume and bag-count estimates only.

Keep Planning Your Concrete Project

Use the calculator, compare footing pages, and keep your estimate practical before you buy materials.

Disclaimer: This page provides planning estimates only. Actual concrete needs vary with excavation accuracy, site conditions, local code requirements, bag yield, and supplier guidance. Always verify measurements before buying materials, and consult a qualified professional for structural or code-sensitive work.