How Much Concrete for a 16x24x48 Footing?
16" × 24" × 48" rectangular footing: 10.6667 ft³ (0.3951 yd³), with exact bag counts and a 10% planning example.
A 16" × 24" × 48" rectangular footing contains 10.6667 ft³ (0.3951 yd³) of concrete before an allowance for excavation variation or spillage. The 16" × 24" rectangle has 2.67 ft² of plan area; the two horizontal dimensions are not interchangeable with the 48" depth.
This is a sizeable pour for bagged mix. Compare the physical handling and mixing time with a delivered-concrete quote, especially if several footings will be placed together. At 48 inches deep, confirm the specified bearing elevation, utility clearances, and safe excavation practices before digging; depth alone cannot validate the design. Footing thickness, soil bearing, supported loads and reinforcement must come from the project design or local authority—not from the bag count.
Quick Answer
One 16" × 24" × 48" footing: 10.6667 ft³ / 0.3951 yd³ before waste. With a 10% example allowance, plan for 11.7333 ft³ / 0.4346 yd³. This allowance is a planning scenario, not a universal requirement.
Without waste: 36 × 40 lb, 24 × 60 lb, or 18 × 80 lb bags. With 10%: 40 × 40 lb, 27 × 60 lb, or 20 × 80 lb bags. Assumed mixed yields: 0.30/0.45/0.60 ft³ per 40/60/80 lb bag; always check the chosen product label.
Need a custom estimate? Use the Footing Calculator, try the concrete estimator for any pour, or browse footing size pages. All project pages.
How to Use This Footing Estimate
Use these steps to plan quantities for the 16" × 24" × 48" footing; they do not replace an approved structural design.
- Verify the design: confirm that a 16" × 24" × 48" footing is specified for the supported loads, soil bearing and local frost/depth rules. Locate underground utilities before excavation.
- Measure the concrete cavity: check clear internal dimensions of 16" long × 24" wide × 48" deep; account for any bell, extra base or irregular excavation separately. A 48" excavation also needs a site-specific assessment of stability and safe entry/access.
- Estimate the concrete: one footing needs 10.6667 ft³ before waste; a 10% example gives 11.7333 ft³. Multiply by the actual number of identical footings.
- Choose delivery: for one footing with 10% extra, compare 40 40 lb, 27 60 lb, or 20 80 lb bags with ready-mix. Check the published yield of the exact bagged product.
- Plan the placement: follow the approved excavation, bearing preparation, formwork, reinforcement and anchorage details. Organize access, equipment and enough help for continuous placement.
- Mix, place and cure: follow the concrete product instructions for water, mixing, placement, consolidation and curing; do not treat a nominal curing age as automatic structural approval.
Formula
Rectangular or square footing volume: length × width × depth, with all three measurements in the same units. To calculate directly from inches, divide cubic inches by 1,728.
In cubic feet: (16 × 24 × 48) ÷ 1,728 = 10.6667 ft³. In cubic yards: the unrounded ft³ result ÷ 27 = 0.3951 yd³. Values shown here are rounded for display; bag counts use full precision.
10% planning example: base volume × 1.10 = 11.7333 ft³, or 0.4346 yd³. Because the allowance is applied to volume before dividing by bag yield, it is not the same as multiplying a previously rounded whole-bag count.
Worked Example
One 16" × 24" × 48" footing: 10.6667 ft³ (0.3951 yd³). With a 10% example allowance, 11.7333 ft³ (0.4346 yd³), equivalent to 40 × 40 lb, 27 × 60 lb, or 20 × 80 lb bags based on standard yields.
Three identical footings: 3 × 10.6667 = 32 ft³ (1.1852 yd³) before waste. Add 10% to the combined volume: 35.2 ft³ (1.3037 yd³), then round up once to 118 40 lb, 79 60 lb, or 59 80 lb bags. This can differ from rounding each footing separately.
Bag Count Estimate
- 20 bags of 80 lb concrete mix
- 27 bags of 60 lb concrete mix
- 40 bags of 40 lb concrete mix
Always verify the actual yield on the product label before buying materials.
Bag Counts by Waste Buffer for 16" x 24" x 48"
These buffers are examples, not a universal recommendation. The right percentage depends on excavation accuracy, how precisely you measured, soil and ground conditions, and placement losses such as spillage or over-dig. This page uses 10% as its own planning figure.
| Buffer | Volume (ft³) | 80 lb bags | 60 lb bags | 40 lb bags |
|---|---|---|---|---|
| No buffer | 10.67 | 18 | 24 | 36 |
| +5% example | 11.2 | 19 | 25 | 38 |
| +10% example | 11.73 | 20 | 27 | 40 |
| +15% example | 12.27 | 21 | 28 | 41 |
When Bagged Concrete vs Ready-Mix Makes Sense
For one footing, the 10% example needs 20 × 80 lb bags, approximately 1,600 lb of dry mix. Compare bag availability, mixer capacity and hauling time with a supplier quote rather than assuming bagged concrete is cheaper.
If there are three identical 16" × 24" × 48" footings, the combined volume with the same 10% example is 1.3037 yd³. Order based on the combined measured cavities, not just the single-footing result; confirm truck access and what the supplier charges for short loads. Neither bag count nor material weight establishes the footing’s load-bearing capacity.
Common Uses for This Footing Size
This is an 16" × 24" rectangular footprint. The longer side may match a particular layout or support detail, but there is no basis for asserting that a rectangle is suitable for a given post or wall from dimensions alone.
The base area is 2.67 ft² and the concrete volume is 10.6667 ft³. This page is useful for estimating a single cavity, comparing alternate depths, or calculating several identical footings. A 48" depth doubles the volume of a 24" footing with this same footprint. Deeper excavation changes handling and site-safety demands; an approved design must establish the depth. Soil bearing, reinforcement, supported loads and local construction rules remain separate design checks.
Common Mistakes to Avoid
For this rectangular footing, avoid these estimating and site-planning errors:
- Treating the 16" × 24" rectangular cavity as a 24" square; use the two actual plan dimensions.
- Ordering bags from a rounded 0.4 yd³ display instead of the precise 16" × 24" × 48" calculation.
- Adding 10% to the already-rounded bag count instead of applying the example allowance to the concrete volume before rounding up.
- Starting a 48-inch excavation without checking utilities, excavation safety and the approved bearing elevation.
- Using a generic bag yield without checking the specific manufacturer and mix type.
- Overlooking bag transport, consistent mixing, consolidation and curing when placing multiple batches.
Frequently Asked Questions
How much concrete is in a 16" × 24" × 48" footing?
A single 16" × 24" × 48" rectangular footing contains 10.6667 ft³ (0.3951 yd³) before waste. With a 10% example allowance, the planning quantity becomes 11.7333 ft³ (0.4346 yd³).
How many bags of concrete are needed for a 16" × 24" × 48" footing?
Without waste: 36 bags of 40 lb, 24 of 60 lb, or 18 of 80 lb. At a 10% example allowance: 40 of 40 lb, 27 of 60 lb, or 20 of 80 lb. These estimates assume 0.30, 0.45 and 0.60 ft³ of yield per respective bag; check the product label.
Does a 48-inch depth double the concrete used at 24 inches?
Yes. With an unchanged 16" × 24" footprint, 24" depth requires 5.3333 ft³ and 48" depth requires 10.6667 ft³. This describes volume, not whether either depth meets the site’s frost or footing design requirements.
Should I use bagged concrete or ready-mix for this 16" × 24" × 48" footing?
For one footing with a 10% example allowance, 20 80 lb bags mean 1,600 lb of dry mix to transport and mix. Get a ready-mix quote and compare short-load fees, site access, pumping needs, crew size and placement timing; several footings can change the decision.
Keep Planning Your Concrete Project
Use the calculator, compare footing pages, and keep your estimate practical before you buy materials.
Disclaimer: This page provides planning estimates only. Actual concrete needs vary with excavation accuracy, site conditions, local code requirements, bag yield, and supplier guidance. Always verify measurements before buying materials, and consult a qualified professional for structural or code-sensitive work.